(a) Draw a simple line diagram of the bow of a ship to show the position of the following components as parts of the ships mooring system: Hawse pipe, Cable stopper, Windlass and Cable lifter, Spurling pipe and Chain locker. (4) (b) Describe the cable stopper and state its purpose (4) (c) Show by means of a sketch how the anchor cable is attached to the ship. (4) (d) Describe how the chain locker is drained of water, sand and mud. (4)

Reference Answer

### (a) Diagram and Layout of Bow Mooring System
A simple line diagram would illustrate the path of the anchor cable from its storage to its deployment into the sea. The arrangement is designed for a direct and fair lead to minimize stress on the components.
1. **Chain Locker**: This is the compartment located in the forepeak of the vessel where the anchor cable (chain) is stowed. It is typically a large, robust space designed to handle the weight and abrasive nature of the chain.
2. **Spurling Pipe**: A heavy steel pipe that leads from the top of the chain locker up to the deck level, directly beneath the windlass. The anchor cable passes through this pipe.