Class 4 (4th Engineer) SSEP 📅 Nov 2025

Exam Question

In engine rooms that are operated under UMS conditions describe with the aid of sketches how the following are monitored:

(a) the perforation of a high pressure fuel pipe. (7)

(b) the imminence or possibility of a scavenge fire. (7)

(c) engine room bilges (6)

Reference Answer

### (a) Monitoring of High-Pressure (HP) Fuel Pipe Perforation (7 Marks)
#### 1. Regulatory Requirement & Principle
In compliance with SOLAS Ch II-2, Reg 4, all external high-pressure fuel delivery lines between the high-pressure fuel pumps and fuel injectors must be protected with a sheathing arrangement. The principle of monitoring is to detect a leak from the primary HP pipe by collecting the leaking fuel within the outer sheath and activating an alarm.
#### 2. Construction & Arrangement

Full answer on MeoMock — surveyor-grade reference answers for 7,000+ written exam questions.

View plans Browse library

← Browse more questions

Prepare on Android — MeoMock on Google Play