← MeoMock / Written exams
Class 4 (4th Engineer) MEP 📅 Nov 2023

Exam Question

(a) Describe the safe isolation procedure of centrifuges on board ships before starting maintenance work. (6)

(b) Describe maintenance schedule of centrifuge for satisfactory operation. (10)

Reference Answer

### (a) Safe Isolation Procedure for Centrifuges
A systematic and rigorous isolation procedure is critical to ensure the safety of personnel before commencing any maintenance on a centrifugal separator. The following steps, incorporating a Permit to Work (PTW) system, must be strictly followed:
1. **Inform and Obtain Permission**: Inform the Duty Officer on the Bridge and the Engineer in charge of the watch (Chief Engineer/Second Engineer) of the intention to stop and work on the centrifuge. Make a relevant entry in the engine room logbook. This ensures the machine is not expected to be in service and prevents inadvertent attempts to start it remotely.
2. **Proper Shutdown Sequence**: Stop the centrifuge from its local control panel. Allow the machine to come to a complete stop naturally. Do not use the brake harshly unless in an emergency, as this can cause undue stress. The rundown time should be monitored; a significantly short rundown time may indicate bearing or friction issues.

Full answer on MeoMock — surveyor-grade reference answers for 7,000+ written exam questions.