Exam Question
The vessel in which you are the Chief Engineer is about to be laid up for 3 months for commercial reasons. All equipment and machinery on board require to be preserved during the lay-up period for re-commissioning when required. Describe the actions you will take as Chief Engineer to prepare the Main Propulsion Diesel engine for preserving during the lay-up period.